STUDIES AND PROPOSALS
For
|
C
R O M A R T Y T E N N I S C L U B |
|
Founded 1902 |
|
 |
|
Cromarty
Tennis Club,
65 Cromarty Street, Sydney, Nova
Scotia, Canada (Image
postmarked September 25, 1908)
|
A
Feasibility Study for A Public Indoor Tennis Facility
Presented By
Eric Krause
Krause House Info-Research
Solutions
For
the
Cromarty Tennis Club
Sydney, Nova Scotia, Canada
April
11, 2006
Revised January 16, 2009
(IV) TECHNICAL ISSUES
NOTE OF JANUARY 16, 2009:
Some of the recommendations
below are now outdated because of later developments.
For example, we have secured a long term lease to property at the Sydney
Airport Authority.
Index To The Technical Issues
(Please Click On The Topic Of Your
Choice):
(A) Location
(Closely
resembles the proposed facility)
Three locations should be
considered:
- Cromarty Tennis Club,
with the structure built in the ravine parallel to courts two and three so as to minimize
any building height issue.
- Sydney area, in a place where
building height would not be a potential, divisive issue.
- On the grounds of CBU
[Cape Breton University]
(i) Cromarty Tennis
Club Area
Malcolm Gillis, Planning Department, Cape Breton
Regional Municipality, has examined the proposed location and anticipates no
problems if the site is properly sited and correctly developed.
The plan is to excavate a site as low
and as cost-effective as possible in
the ravine to the west northwest, opposite of,
and parallel to courts two and three.
(ii)
Sydney Area
The
possibilities are endless, but any site must be zoned to allow for a
public recreational facility of the proposed size and height, with immediate-close
proximity to a publicly plowed street or highway. One option would be
on CBRM property that allowed the same land leasing arrangement as with the
existing Cromarty Tennis Club. To encourage high winter membership
numbers, and produce relatively short winter driving distances, the site should
be located in the immediate Sydney/Sydney River/Grand Lake area where the greatest population
density of the CBRM exists.
(iii) CBU [Cape
Breton University
CBU is presently studying
the possibility of clustering a number of recreational facilities on its
grounds in the interest of promoting health and wellness. By a motion of the
Cromarty Tennis Club on June 27, 2006, the executive authorized Eric Krause
to sit on a committee struck by CBU to examine the feasibility of this
proposal. On June 30, Eric Krause met with Gordon M. MacInnis,
Vice-President, Finance & Operations, who invited him to join the committee.
Mr. MacInnis will also ask Donnie MacIsaac, Facilities Manager, CBU, to
examine Mr. Krause's report "A
Feasibility Study for A Public Indoor Tennis Facility"
to determine if such a building could be constructed on the grounds of the
university. Presently, the committee is at the visionary stage and no
financial commitments have been discussed.
Because the clustering
will depend on the strengths of many organizations, including
non-profit societies, the "Cromarty Community Indoor Tennis Centre" will
have a key role to play in the raising of funds and the making of
operational commitments that will determine whether an indoor tennis
facility can be feasibly constructed at CBU.
(B) Land Preparation
(i) Cromarty Tennis
Club Area
Access to the work site
can be by means of the
existing roadway to the south southwest of the present club house. Any initial fill
required for site preparation and making it flat and ready to
receive a concrete slab on grade will come from excavating
the side of the gully itself.
The idea here is to take the
sub-grade opposite courts two and three to as low in elevation as is
practical and cost effective. To the west
northwest,
next to the building, a
raised tail will remain to maximize the brook's flood plain in keeping with the
recommendation of the Planning Department, Cape Breton Regional Municipality.
In the excavation work
there will be a need for drainage facilities.
By locating the building
where illustrated the idea is to economize on land preparation costs by
minimizing the amount of excavation (particularly rock removal) and the
extent of an assumed, potentially expensive, retaining wall to the
east southeast of the building.
(ii) Sydney Area
A flat site would
greatly economize the initial cost of the public facility.
(iii) CBU [Cape
Breton University
A flat site would
greatly economize the initial cost of the public facility.
(C) The Building
In any location, the building
- housing a doubles court
measuring 60x120 or 7,200 sq. feet
- must be secure from vandalism and break-ins
(i.e. certainly not of fabric or wood
excepting perhaps at a patrolled CBU site), permanent in nature
(20-40 years), generally
maintenance free, fire-proof, economical, easily accessible, and usable
year-round. Without doubt, an insulated pre-engineered
steel structure (kit) without windows or skylights, and with as
low a pitched roof as possible (or
arched roof) would meet these
requirements. At a CBU site, where security would unlikely be
an issue, a bubble or
a fabric frame structures (tensioned fabric)
might become a possibility
vis-ΰ-vis that of a pre-engineered steel structure if their lower capital
costs were to trump their problematic shortcomings in the areas of long-term
permanency and fireproofing.
At this point, there are many considerations
to keep in mind:
(i) Ground Footprint
A court placed in a "minimal-sized" building
(outside measurements of 60x120 [7,200 sq. feet]) to one located in any size
larger is clearly one of choice based on many factors.
Obviously capital and operational economy is
the prime consideration when choosing a minimal-sized structure and, if
well-planned, could be the best choice. A larger structure, though less
economical, would enhance the actual playing area (e.g. more run-off space),
and allow for more amenities.
Perhaps the largest footprint for
consideration on the Cromarty Tennis Club site ought to be 80'x140' [11,200 sq. feet].
This footprint would allow for an additional area for judges, a safe
over-run for players, washroom facilities, storage, benches, water coolers,
or trash cans, for example.
(ii) Interior Height
The official recommendation
for pre-engineered steel building is for 18 feet
high at the eaves, 20-21 feet over the baseline and 35'-38' over the
net-line. The standard for a bubble is 36 ft. high with
as deep sidewalls as possible to maximize sideline clearance, vertical ball
flight, bubble stability (in high wind), insulation values, energy
efficiency (easier on air pressure equipment) and snow removal.
(iii) Building Types
(a) Pre-engineered rigid framed
[General Building
Manual:
http://acemetalbuilding.com/Generalerectionmanual.htm ]
The traditional pre-engineered steel
"wide-span" frame chosen for many tennis
facilities around the world would not be the best choice for a minimal-sized
public facility
[60 feet x 120
feet] since its many multiple spaced interior wall columns would not
only intrude into the interior's 12' sideline but also introduce a safety
concern here. In contrast, a pre-engineered steel "long-bay" structure would
be better, as this type building would reduce costs [less steel], maximize
interior space and safety [here wall columns are spaced 50'-60' apart
allowing for the two center columns to be
located opposite the net posts], and
would speed up
assembly [lessen labour costs].
On the other hand, a building that measured
80' wide x 140' long could be either
"wide-span" or
"long-bay" [See also:
American Sports Builders Association], with the
final purchase and assembly cost perhaps being the only determining factor
in choosing between these two types of pre-engineered rigid frame
structures.
One style of "wide-span" building
allowing for a high ceiling is the Olympia Steel Building
System [a rigid frame, plate steel, H or I beam construction]. It is a
flexible building design produced from top commercial grade U.S. steel, with
a 25-year "Galvalume" roof sheeting
warranty and with a company experience
of over 30 years of
construction history. [
http://www.olympiabuildings.com/
]. The sides and ends of the building
have a 30-year baked on paint warranty. Olympia's Factory, Steel Built
Corp. is also CSA-A660 Certified :
http://www.olympiasteelbuildings.ca/certification.htm
On November 24, 2008, I received the
following upon a request (60'x120' and 80'x140') which I made to Olympia
Buildings:
Hello Eric,
I have attached the
quote and drawings you requested. There is not 25 clearance
under the haunch of the rigid frame. The outside walls are 25, but
inside it is lower. If you need 25 and 35 feet clearance, I will
have to build them a little bigger. This will still give you a good
idea. More detailed drawings are going to arrive by mail. Thank you,
Jack Evans
Olympia Steel Buildings 866 479-3292
Toll free office ; 905 479-8099 Local office ;866 479-3293 Toll free
fax
A similar style is produced by American
Steel Structures [
http://www.americansteelstructures.com/
without
any details regarding an insulation package. It however has a 25 Year "Galvalume"sheeting
Warranty.
Whether the rigid-framed building
measured 60'x120' or 80'x140', an interior height of 35'-38' can be
easily achieved in either
the "long-bay" or "wide-span" styles.
The roof of a
rigid-framed public tennis facility would ideally be low-pitched, with a ratio
of 1:12 (the lowest, and most economical) perhaps being sufficient.
Allowing snow to remain on the roof would enhance the
insulation values of the structure, though it could obviously introduce
other problems (such as threat of collapse from excessive weight or of
water leakage) if of a poor design.
However, in actuality,
the combination of eave height, size of building footprint, and the need
to meet the required interior height dimensions for a tennis court will
determine the actual pitch.
Olympia Specifications
on Two Building Sizes
[Note: Please Do
Not Print from Your Browser - You Will Need An Image Program And You May
Need to Scale Each Large Jpeg To Fit A Page]
Please Click
On An Olympia Building Image To View It In Your Browser
(b) Pre-Engineered
Metal Rib Arch ["Quonset"] Style
This all-steel
building style features clear-span,
one that maximizes interior space [e.g. Q Model],
and can carry a 30-year warranty
against perforation [e.g.
http://www.americansteelspan.com/
or
http://www.steelmasterusa.com/
or
http://www.amsteel.com/q.htm
]
with "galvalume"
technology, will accept conventional
insulation, features a remarkable ease of erection, and is stronger than
I-beam buildings. Thus great savings in assembly are possible, and the
building is virtually maintenance free when completed, and designed to
withstand the harshest weather conditions. End walls have
a 25-year paint warranty.
Because the height of such a building is
limited to half the span or less, the building need be 70' wide to achieve
the minimum recommended height at the centre of the court of 35'.
(c)
A Bubble (Air Supported)
An air supported
fabric structure is a unique building system that has a proven track
record as a venue for indoor winter tennis and is composed of the
following building components:
1. Fabric enclosure
2. Building anchorage system
3. Air supply system
4. Controlled means of access and egress
5. Lighting system
At least a 5-year
fabrication warranty should be sought, with all seams dielectrically
welded to maximize water tightness. One example would be a long wearing
vinyl-coated polyester fabric (a weight of 32 oz. per square yard is
recommended) so
as to provide the necessary tensile and tear strength, fire resistance,
adhesion and joint strength for the outer membrane.
The outer
membrane (which come in a variety of colours, weights and levels of
translucency [Note: opaque is highly recommended for lighting and
temperature control considerations]) must be flame retardant, treated for resistance to UV,
cold cracks, mildew and chemical pollutants. The warranty for the top
finish must be at least in the range of 10 to 15 years.
The inner membranes,
including the innermost liner [Note: multiple interior layers can
provide added insulation], are made from similar but
lighter fabrics (an 18 oz material is recommended)
and provide improved insulating and acoustic
characteristics.
As with
pre-engineered structures, within the bubble there ought to be a
contrasting color to a height of 10 to 12 feet to provide a backdrop
which improves ball visibility from the court with the remainder above
of a highly reflective white color to maximize lighting.
Both a primary
and a standby mechanical system ought to be provided
with each
device
capable of providing full
inflation pressure to the
bubble.
A controlled
means of access and egress is a
necessity to minimize air pressure loss.
A system such as designed by the
Farley Group
specifically for tennis [
http://www.thefarleygroup.com/aboutus/whatsthat2.html ] is highly
recommended.
(d)
Fabric Frame Structures (tensioned fabric)
These structures, combine a
metal frame structure and fabric panels that are stretched to form a
rigid building envelope and thus help to
eliminate the concern over collapsing under heavy snow or wind loading.
They have a life of 15-20 years
and cost less than rigid framed buildings.
See also:
www.summitstructures.com
Their portability, light-weight
construction and minimal foundation requirements also make them an
excellent choice as a temporary all-weather building where initial cost
is a consideration or where short term use is anticipated.
The frame must be
corrosion-resisted treated. For example, the steel frame may be coated
using shot blasted and epoxy painted or may be hot dip galvanised.
Often the steel frame
consists of a latticework superstructure. The building is then covered
with a tensioned heavy duty PVC white translucent roof membrane
with an acrylic topcoat cladding that projects against ultra-violet
rays, and its mildew-resistant and fire retardant.
The latest
polyethylene fabric welding technology is a must.
The Rubb Building
System (England) is highly recommended. See
Technical Specifications (pdf file)
(D) Thermal Insulation
Proper insulation is a critical
cost-saving application.
A radiant barrier
type rather than a traditional form works best in both a winter and
summer environment. [For example, see:
http://www.premiersteel.org/Insulations.html . See also for tennis
insulation:
http://www.a-ztech.on.ca/insulation1.htm ]
(a) Pre-engineered
Steel
Modern pre-engineered
buildings have developed insulation systems that cover
some or all of the roof structure from below. One type fills the space
between the roof deck and the bottom of the purlins with insulation, which in
turn is held in place by reflective white fabric with the
main beams left exposed. In another system - the better of
the two - the entire faced insulation blanket is suspended beneath the
bottom of the main frames, so that no roof structural steel is visible.
The Olympia
steel building, for example, offers three types of insulation: a vapor-lock composite
insulation which consists of polyethylene air bubble pockets sandwiched between
thick layers of reflective coating; a traditional WMP-VR fiberglass insulation
which comes in a range of "R" values [for example:
R-7 = 2" of insulation; R-19 = 6"]; and a premium insulation system designed
to fit snugly between roof purlins to remain compression-free. This premium
insulation package gives a finished look to the building's ceiling while
providing the roof with a high insulation value of R-40 [12 inches].
The wall insulation application will require a
vapour barrier [vapour retarder] that complies with fire standards and is
puncture-proof from tennis balls. Its colour must contrast with the ball
to a height of approximately 12' - 14' directly behind the court, high enough so
that the background colour is behind the ball on the service toss. Above these
levels [that would include all structural members as well as the vapour
barrier], up to the level of the ceiling, it should be of a very light matte
finish of uniform colour.
On the walls adjacent to the length of the court (at the
ends of the building), the contrasting colours should continue to at least the
baseline of the court.
The walls of the Olympia steel building can take
9 inches of insulation [R-30].
The fibre fabric over the girts of the Olympia
system produces a white finish in the building on the roof and the sides.
Pre-engineered metal rib arch buildings
are generally compatible with conventional insulation methods and,
if purchased as a kit, the structure must be supplied ready-engineered
to receive fiberglass bats.
Because this public facility will
have neither windows nor skylights, thermal insulation efficiency will be
increased accordingly.
Furthermore, the lower the roof pitch the more the amount of
snow that would remain on the roof and the higher the building's insulation values
would be.
Finally, an insulation
package will also provide condensation control
and prevent moisture from dripping onto the court below.
(b)
Bubble (Air
Supported)
Multiple interior layers provide added insulation through the trapping of air between
membranes. An interior lining may also have insulation. Without such
precautions, the R-Factor value would be no higher than 4.
(c)
Fabric Frame Structures (tensioned fabric)
Translucent fabric
allows sunlight to penetrate, which may help light and heat the
building, thus reducing utility costs. The fabric does however block
harmful ultraviolet rays.
Better though, the roof is
able to have an insulation layer between the two layers of
premium fabric, which span the inside, and
outside. An inner
building insulating liner that may be installed would increase the
insulation to 3.1 W/m2K [UK R value measure] while also hiding the steel
trusses if aesthetic requirements were important.
Profile steel cladding can be specified
to the building to ensure the building is protected on non-secure sites.
Likewise, the side panels are often removable
making these structures ideal for summer play as this
creates well-ventilated air without the
sun.
(E) Foundation Work
Although the type and cost of
foundation work will vary by the type of building required, both the
pre-engineered rigid frame and the metal arch style can utilize the floating
slab system rather than perimeter foundation walls (frost walls) at great time
and labour cost savings.
In this system, the floor will consist of a floating slab
(that is, a slab on grade) with a vapour barrier. It can be poured
monolithically with the foundation wall, or poured after the foundation wall
is in place. In both cases, the concrete slab encases steel serving as
reinforcement. This steel reinforcing will reduce the cracking of the floor
and help control expansion and contraction. Its thickness will be determined
by its use as a tennis court.
Monolithically
poured with a continuous grade beam is recommended. The grade
beam can be spread under the column or reinforced along the bottom to carry the
vertical column loads.
The edge of the slab on
grade must be insulated (insulation skirt) to prevent thermal bridging.
Anchor bolts or
foundational industrial
arch connectors may or may not be included in the frame kit.
(i) Pre-Engineered
Rigid Framed
The Olympia style building,
for example, is a steel framed building which has point loads at
column locations. Because a rigid frame structure is far
more affected by horizontal rather than by vertical loads, its footings must incorporate steel tie-bars.
If the expected horizontal loads are
excessive, the footings may need
also to be
increased in size (which will increase costs).
(ii)
Pre-Engineered Metal Rib Arch ["Quonset"] Style
Ease of construction is the hall-mark of
this style: Pour a simple floating foundation, bolt arches together on the
ground and simply raise the arches into place and secure
with foundational industrial arch connectors.
(iii)
Bubble (air supported)
A continuous concrete
grade beam around the base of the building is a basic requirement for
anchoring the structure, with an additional anchorage system
called "stress relief" strongly recommended.
(iv)
Fabric
Frame (tensioned fabric)
A full range of
designs are possible from earth anchors to concrete.
(F) Lighting
The goal is for lighting that
is uniform and glare free.
Because outside lighting
by
means of windows in the wall or skylights in the roof is much more intense than indoor lighting, causes an
undesirable contrast, varies
in intensity, is undependable,
and may cause glare, condensation and maintenance problems,
none are required.
The lighting system that will be initially
installed will take an energy efficient form that can easily be enhanced at a
later date if desired. The idea here is to get the most light out of the least
number of fixtures with 70 to 100 foot-candles being the standard for
recreational play (125 deemed excellent).
"Indirect" lighting
(uplighting) aimed at a reflective white surface is preferred. This would rule
out the historic use of common fluorescent fixtures 13'-22' over the court
surface and outside the alleys parallel with the sidelines of the court even if
they were louvered
and made use of three phase wiring to eliminate
flickering. Ruled out too should be high intensity discharge (H.I.D.)
"direct" lighting fixtures.
Metal Halide lamp fixtures
have been a traditional feature of indoor tennis for a long time now, but bulb
output is yellow light, it depreciates quickly, and lasts 12,000 hours. They also
require a warm-up period.
At a considerable cost
savings is the T5 fluorescent blue light technology [like the impact resistant Courtlite
indirect lighting system] that produces excellent lighting
levels without creating shadows on the ball. [
http://www.courtlite.com/main.htm
See also: Courtlite.pdf -
robin@pacificenergysolutions.com
]. Significantly, these lights can be dimmed or switched separately [i.e.
capable of producing multiple light levels from a single fixture] to handle
non-tennis functions more economically. Bulb output is a more eye friendly blue
light, it depreciates slowly, and it lasts 20,000 hours. Strung anywhere from
16' to 26' above the floor and 6' beyond the sidelines, in a 60' x 120'
building, lighting location could be problematic though if installed directly on the
walls, with the light properly angled towards the centre of the courts ceiling,
this system should produce a proper lighting level.
In any chosen lighting
system, ease of re-lamping and keeping fixtures clean without any elaborate
access system is essential.
In some steel buildings with
exposed beams, a suspended ceiling system may be required to increase light
efficiency. On the other hand, ceiling reflectance can vary from 60 to 90
percent, depending on whether there is a suspended ceiling, whether the roof steel is painted,
or whether the roof steel is covered with an insulation application of highly
reflective facing fabrics.
While many control devices are available, it is
recommended that lights be placed on a non-cash timer to enhance their cost
effectiveness while not encouraging break-ins.
(G) Ceiling
A
suspended ceiling would be
required in some construction types chosen for a public tennis facility. Consisting of fibreglass insulation with a highly reflective reinforced white fabric which is
resistant to ball puncture, a hung ceiling would control condensation (particularly in the
winter), provide a vapour barrier that would keep the courts dry and free from discolouration, protect the building's structural steel from deterioration, and
improve the lighting of the court itself .
However, a ceiling would not be required
in any building type designed to use something like the
white Olympia insulation package. [See Thermal Insulation section]
(H) Heating and Cooling (Thermal Energy)
The heating system ought to
take a basic form, given the understanding that an
enhancement may be desired at a later time [see HVAC below].
(i) High-Intensity
Infrared
For certain, a
propane gas-fired
high-intensity
infrared radiant ceramic ["light"] heating
system would be an excellent initial choice. Since a radiant
system
heats objects first and air only secondarily, infrared ceramic heating is a
most efficient regime for
keeping players warm. [For example -
http://store.h-mac.com/momtprornaga.html or
http://www.spaceray.com/industrial/ceramic.html . Locally, Superior
Propane can supply a similar Canadian product (902-539-1061)]
Infrared ceramic heaters
also have a very fast
warm-up time, and can be switched off and on during a playing session, but must
be installed only in a "non-flammable" structure.
The high-intensity type heater is better
suited to well-insulated buildings with high ceilings [thus a high air
volume] than their low-intensity tube heater cousin.
The ceramic units are compact, operate
without noise, and can be located along the ends of courts, where they can
effectively heat the public facility without the need for noisy blowers or fans.
In heating an entire building, the
system is designed to heat the floor, which, in turn, creates convection
currents that heat the air above it, which is ideal for
tennis players.
The high-intensity ceramic
heater will require indirect ventilation through ceiling-mounted exhaust fans or
through natural infiltration [minimum of 4.18 CFM per 1000 BTU per hour of total
installed heater capacity on propane].
Incidentally, the Metal Rib Arch ["Quonset"] Style
is designed to accommodate turbine vents every 20 feet to remove condensation and maximize air circulation.
Ceramic heaters may also
require a reverberatory
screen to increase overall emissivity of the radiant surface and also serve as a
protective barrier against tennis balls.
In a
minimal-sized building, which has only a 21' back space,
where precisely ceramic heaters might be placed
could be an issue, but their compact size and recommended
minimum clearances from combustible materials would certainly facilitate matters.
(ii) HVAC
Clearly, the ideal
heating system would be a HVAC
(Heating/ventilating/Air-conditioning) regime that would heat and cool the
building to maximize year round player comfort.
An HVAC system capable of holding a
building to a temperature ranging
between 55 to 62 F degrees [12.7
to 16.6 degrees C] during
winter,
and 10 to 15 degrees below the outdoor
temperature during summer, to a humidity level of 55%
to 60%, while changing the air within the building 6 to 8 times per hour at minimal noise
levels and without creating a draft on players would be best.
(iii) In-Floor
Radiant
A third heating
possibility is in-floor radiant heating.
In-floor elements that heat the mass of a
concrete slab has an almost immediate recovery rate. For a thick concrete
slab, hydronic radiant systems are popular. Here warm water circulate
through continuous circuits of polymer or synthetic-rubber tubing, with the
cold water returning via a manifold back to a boiler to be reheated. The
downside is that because of the thickness of the required slab in the case
of the proposed public facility and the fact that this thermal mass is slow to
respond to thermostat changes, the indoor temperature will need to be kept
stable, even when the building is not in use. In other words, prolonged
setbacks (overnight or longer) at temperatures lower than playing
temperatures may not be desirable.
An option would be to lay
the tubes in the matrix of the cushioned floor itself, but here the
manufacture of the court surface would need to be consulted to ensure not
only that this was possible (i.e. what is the thermal resistance of such a
floor), but also that it would not affect the playing characteristics of the floor
itself.
A hydronic radiant system
would also require a mechanical room to hold all of the equipment: Boiler,
pump, valves, manifold, expansion tank, etc.
(I)
Plumbing
(i)
Wash Room
A basic washroom
amenity is recommended.
Clearly, in a minimal-sized
all-year round building,
a "public" washroom - meeting CBRM
Building Code - might need to
be in an appendage
attached to, or in an outbuilding separate from, the main structure.
If it were desired not to
bring water into the main building, or if a minimal-sized building was
assembled, a waterless remote electric Envirolet compositing toilet that is
ideal for cold temperatures, and need not be emptied all winter, might be a good
choice despite its relatively high initial cost. [
http://www.envirolet.com/enwatremsys2.html
]. This system however requires the building to be above ground or with a
basement.
Also, where "green" is preferred in some grants, this amenity could improve
the chances of an application being approved.
(a) Cromarty Tennis
Club Area
During the summer season, the washroom (and shower) facilities of the Club
House are available to both programmes, but in the cold months, its plumbing
system must be winterized since the building has neither furnace nor insulation.
Located
inside or outside the public tennis facility, a basic washroom would also be
useful to the summer programme.
(J) Wiring
Installation
The highest
available service should be chosen to reduce wiring costs. Three phase wiring to eliminate
flickering may be required if fluorescent, mercury or high
sodium lighting is chosen, with each alternate fixture on a different phase.
Such wiring simplifies power distribution,
allows court lights to be dimmed or switched
separately, and
reduces the amount of wiring. Also, should a HVAC heating/cooling system ever be installed, it
can be relatively small and light, a distinct advantage in a minimal sized
public facility.
(K)
Automatic Active Fire Suppression System
Insurance may or
may not require an automatic active fire suppression system. Wet and dry pipe
and mist sprinkler systems should be avoided if
at all possible for all kinds of capital and operating cost reasons, and if building design features
(e.g. passive fire suppression and fire proofing materials) can be introduced to ensure that one was not required, this would be best.
If a system were however necessary, Halon 1301 is not an option as it is
environmentally damaging.
(L) Security
and Fire Monitoring; Lock and Key System
The interior of the
building must be monitored by an outside security firm with an
interior entry /exit security/monitoring system
that records every security-on and security-off
action, alerts when there is an intrusion, and detects smoke
and heat. The phone line should be underground until it is inside the public facility
where the main telephone junction box is located so that it cannot be tampered
with on the outside.
(i) Cromarty Tennis
Club Area
The system should be bundled with a similar one for the
summer club house and external gates to maximize savings and maintain
consistency.
The club house,
external gates, and the
public indoor facility should be each fitted with the same lock and key system.
Although both a non-mastered lock system (restricted key-blank or "do not
duplicate" system) and the master keyed lock systems are vulnerable to
duplication, the stamped "restricted key" system combined with a different interior
entry /exit security/monitoring system
should provide adequate security. In addition - and to keep
in mind - some lock manufacturers make their restricted key security service
available only to one selected locksmith in an assigned area, and require on
file a signature to compare to and verify against before cutting a duplicate.
(M) Court Surface
- Cushioned Court
The offering here would produce a 60 foot x 120
foot doubles court dramatically unlike the four existing outside
"Tru-Plex"
[plexi-pave acrylic] hard
courts that would appeal not only
to the competitive and recreational
player alike, but also to beginners
and the older members. It
is a fact that today a growing number of people are turning to facilities
which feature more friendly court surfaces such
as cushioned surface systems to
minimize physical effects - i.e. reduce aches and
pains - especially to ankles, knees, and hips;
and keep one cooler,
out of harmful sunlight, and swirling winds. Clearly if the Cromarty Tennis Club were to enter
this environment with a cushioned tennis court available to the general public
and an aggressive marketing strategy, its appeal to use it rather than other
recreational facilities -
especially in the winter - with a reasonably priced offering would be quite
high.
A cushioned court choice, for
example, could be a version of Novacrylic. As described in company literature:
"Ultracushion - The ultimate
acrylic shock absorbing surface. Great for indoor and outdoor courts. A
combination of various EPDM rubber granules encapsulated in a special super
flexible 100% acrylic binder give Ultracushion the ability to provide a high
level of comfort to the tennis player. This all-weather system retains the low
maintenance, durable features found with all Novacrylic surfaces. Ultracushion
courts play slow and the ball bounce is such that longer rallies are possible.
This makes the game more pleasant for most players. Many tennis players have
said that they were less fatigued and felt better after playing on an
Ultracushion court than on other all-weather surfaces." [
http://www.novasports.com/products_NOVACUSHION.htm
]
See also Plexicusion
"Prestige":
http://www.plexipave.com/systems/tennis/plexicushion/plexicushion.html
In particular, any cushion
system will reduce shin splint injuries,
provide a sure footing that does not "stick", reduce
tennis fatigue, and ensure a better workout than hard
courts. And, as a bonus, tennis shoes will last longer.
(N)
Interior Amenities
(i)
Tennis Court Equipment
Besides a net
and posts and associated hardware, little other equipment will be required.
(ii)
Miscellaneous
A rigid framed
building with interior wall columns will require that they be padded with shock-absorbing foam rubber at least 2 inches thick.
(O) Access to the Building
(i) Cromarty Tennis
Club Area
Volunteers will need
to maintain a pathway from the Cromarty Street
exterior gate (accessed by key) next to the existing
summer Club House, to across and
down the deck to beside the south southwest end of Court Two
and from there over towards Court Three and onto the
entrance of the new public facility (opened with the same key as for the Cromarty
Tennis Club's exterior gate and Club House).
(P)
Landscaping
(i) Cromarty Tennis
Club Area
Three walls of the building would form an
effective exterior
perimeter barrier with the fourth, the east southeast side
wall, incorporated into the existing fenced-off summer
area of the Cromarty Tennis Club. Here, some
minor, additional
security fencing will be required to
prevent external access to the outdoor courts.
Galvanized
chain link and post fencing meeting normal industrial security would
be acceptable: For example, perhaps 9 gauge 2" mesh with the top rail of 1
5/8" pipe, line post of 2 3/8" pipe, and terminal post of 2 7/8" pipe
with at least a 12-year warranty is recommended. The height of the fence
need deter intrusion in an area which cannot be observed from Cromarty
Street.
(Q)
Meeting of Standards

|