STUDIES AND PROPOSALS
For
|
C
R O M A R T Y T E N N I S C L U B |
|
Founded 1902 |
|
 |
|
Cromarty
Tennis Club,
65 Cromarty Street, Sydney, Nova
Scotia, Canada (Image
postmarked September 25, 1908)
|
A
Feasibility Study for A Public Indoor Tennis Facility
Presented By
Eric Krause
Krause House Info-Research
Solutions
For
the
Cromarty Tennis Club
Sydney, Nova Scotia, Canada
April
11, 2006
Revised: January 16, 2009
(V) FINANCIAL ISSUES
NOTE OF JANUARY 16, 2009:
Some of the recommendations
below are now outdated because of later developments.
Index
To The Financial Issues
(Please Click On The Topic Of Your
Choice):
(A) Capital Costs
There are a finite number of
capital costs which should be determined and
amortized over 20-25 years as a
yearly cost.
Naturally, any non-repayable matching
or lesser grant from a federal or provincial capital programme which the business plan might identify as available could serve
to significantly reduce this charge.
As well, both a
business
plan [BusinessPlan.pdf] and a
marketing plan [MarketingPlan.pdf] may be required to actually
gain such government funding.
Furthermore, fund raising
efforts could also substantially reduce this capital burden. Fund raising -
spurred on by the fact that the CCITC had a tax deductible charitable status -
would include, but not limited by, gifts from individuals, or gifts from
corporations or businessess.
(i) Capital Cost
Reduction
(a) Nova Scotia
Grant
For example, the Nova Scotia Government,
Office of Health Promotion (Coleen Chisholm, Regional Representative,
Cape Breton Region Contact Person -
Chishoco@gov.ns.ca ), has several programmes designed to assist community incorporated
not-for-profit societies in the construction, and acquisition of facilities
for public recreation purposes [See
http://www.gov.ns.ca/ohp/physicalActivity/grantsCapital.asp
for details]. Here, in summary, an applicant may apply as follows:
To the
"RECREATION FACILITY DEVELOPMENT PROGRAM" for up to 1/3 of the total cost of
the project. The deadline is the first Monday in February of each year.
Applicants are only eligible for either the Community Recreation
Capital Grant Program or Recreation Facility Development Program,
once in any four year period.
To the
"PLANNING ASSISTANCE PROGRAM" for up to 50% of the total cost
of a consultant's, professional engineer, or architect's fee, or up to $5,000 in planning for a proposed facility
(i.e. feasibility study). This aspect must be tendered (at least
three estimates). Applications are possible year round. Applicants
are only eligible for either the Community Recreation Capital Grant
Program or Recreation Facility Development Program, once in any four
year period.
To the
"COMMUNITY
RECREATION CAPITAL GRANTS PROGRAM" for small scale programs for 1/3
of total capital cost to a maximum of $3,000. Applications are possible year
round. Applicants are only eligible for either the Community
Recreation Capital Grant Program or Recreation Facility Development
Program, once in any four year period.
(b) Canada -
Nova Scotia Grant
Here the "MUNICIPAL
RURAL INFRASTRUCTURE FUND" is a possibility". For example see:
http://www.mrif.ns.ca/ where
the objective "is to construct, restore or improve recreation, physical
activity and sports public Infrastructure to encourage a higher
proportion of Canadians, from all segments of society, to integrate
sports and physical activities in their daily life. ... The total
funding from all federal sources will not exceed fifty percent (50%) of
the total Eligible Costs for a Project. ... Please note that projects
must be duly authorized by the project’s local government by way of an
approved resolution by the Municipal Council ... Sufficient information
must be included on the application form to support the rationale for
the proposed project and to provide evidence of a commitment by the
applicant to pay their share of eligible costs and ongoing operating
costs ..."
(c) Canada -
Cape Breton Grant
ECBC funding help is,
of course, always a possibility. For example, see:
http://www.ecbc.ca/e/default.asp
(d) Information and Resources
on Financing a Business in Nova Scotia, including guides on different
forms of financing and sources of funding:
http://bsa.canadabusiness.ca/gol/bsa/site.nsf/en/su06895.html
(e) Cromarty
Community Indoor Tennis Centre Fund Raiser(s)
There are currently
numerous high-dollar fund raising drives underway in the CBRM area.
Houses, condominiums, cars, and 50/50 give-aways seem to be everywhere
and the market here may be close to the saturation point.
(ii)
General contractor
It might be wise to
retain a lawyer to write up a contract(s), whether the Cromarty Community
Indoor Tennis Centre hires a general
contractor or instead acts as its own general contractor. While the cost of any
project consists of labour, materials, profits, and overhead, before actual
construction on the public facility were to begin, all costs are only estimates.
Thus there are financial risks here in who is to pay for any cost over-runs
or who retains savings if the project were to come in under estimate. It
should also be determined what aspects are to be payment in a lump sum
(stipulated sum), in a unit price (piece work), in guaranteed maximum price
(profit limited to a specified amount), or cost plus, all best handled by a
lawyer.
The lawyer should also
determine whether it would be prudent to purchase default insurance to cover
the general contractor and sub-contractors.
(a) Hire
The hiring of a
general contractor may be the best decision to be made despite the
increased cost.
(b) Act as Own
Project Manager
If the Cromarty
Community Indoor Tennis Centre were to
act as its own general contractor and project manager, financial savings
could be made here, though there are also costly dangers if inexperience
became an issue. Thus the following should be examined closely for
guidance:
-
Nova
Scotia Government Construction Contract Guidelines (a.k.a. Request
for Quotation (RFQ), Invitation to Tender (ITT), or Request for
Proposals (RFP) [TenderGuideline.pdf]
- A bid document
ought to include technical, operational and performance
specifications as well as financial and contracting requirements.
For example, see the
Cambridge Ontario tender and quote for
the construction of three outdoor tennis courts (CambridgeOutdoorCourts.pdf)
One savings would be
the mark-up of
the public facility charged by the general contractor (need not be paid). However
numerous responsibilities would return to the Cromarty Community Indoor
Tennis Centre, including project
design, the resolution of design conflicts, the identification of
accidental construction deviations, sub-contracting out, the ordering of
materials (at discount without a general contractor mark-up), the
estimation of the project cost, the scheduling of subcontractors, the
resolution of scheduling conflicts, the keeping of the job process on
time, and the daily on-site inspections of the work to ensure that the
next scheduled item was done properly.
Other savings are
possible too if the Cromarty Community Indoor Tennis Centre itself were to undertake assorted
work: e.g. site preparation, site clean-up, or installing doors.
(iii) Land Preparation
(a) Cromarty
Tennis Club Area
Excavation, drainage and
retaining wall work costs are the greatest unknown, and may require a
drilling probe investigation to determine the extent of rock and the degree
of difficulty in arriving at the necessary level site required for
foundation work.
(b) Sydney Area
A flat site would
minimize land preparation costs.
(c) CBU
A flat site would
minimize land preparation costs.
(iv) Building (Purchase)
(a) Rigid Frame
The initial capital cost of this building
will contribute to approximately 1/3rd of the total cost of the
public facility
over 20-25 years. Thus future savings are possible
here if the initial design allowed for cost effective installations
in the first place in the area of lighting and heating.
Between $9 and $13
USA per square foot for a
rigid-frame structure, and between $4 to $12
USA per square foot for a metal
rib arch building, is an industry standard south of the border.
This includes materials and delivery
(but not the slab or insulation). So, for a building of 7,200 square feet
(60'x120'), with a high ceiling, perhaps $72,000 USA would be an average
figure, with the larger the building the less cost per square foot.
(a) Bubble
It offers significant
advantages over a pre-engineered building with its low cost, its ease of
relocation, its expandability and its clear open playing space. The
larger the size of the bubble the smaller the cost of each square foot
covered. Costs generally range from $8.00 to $10.00 USA per square foot
for the building alone, depending on the overall size and configuration
of the building (i.e. $58,000 to $72,000 per court).
(v) Building
(Assembly)
(a) Assembly -
Rigid Frame
Joneljim would
assemble a rigid-frame building for a ball-park figure of $50,000.000 CND plus HST. Here then, the labour charge works out to be approximately
$6.67 CND plus HST per square foot. For a rib arch style building, the
labour charge would be significantly lower. The labour charge clearly
should not exceed the cost of the kit.
(vi) Thermal
Insulation Work
(a) Insulation
Materials and Insulation Labour
The labour and
materials charge may be:
(vii) Foundation Work
Joneljim has
"ball-parked" a charge
for concrete with a reinforced slab on grade (assuming a flat site) as $135,520.00 CND plus HST
for a building of 120' x 60'. Here
then, for the concrete work, the per square foot charge is approximately $18.82 CND plus HST
. For a rib arch style building, the concrete price would be approximately the same. These
figures were checked with a second
engineering source and appear in line with Cape Breton pricing practice.
Here the figures would be 167 cubic metres of concrete @ $400.00 CND per
cubic metre or $67,000 CND plus the cost for reinforcing materials (e.g.
wire mesh and steel rebars) which would increase that charge to at least
close to that of Joneljim's all-inclusive slab estimate.
Because anchor bolts or
foundational
industrial arch connectors may or may not be included in the frame kit, this
cost may need be included in the foundation cost work. For example, anchor
bolts would need be set plomb during the pouring of the concrete.
(viii)
Lighting
One doubles indoor court
would, for example, require fourteen impact resistant fixtures (indirect
base), each with a 1,000-Watt Metal Halide lamp which, at c. $500.00 USA
each, would cost c. $7,000.00 USA.
The initial cost of T5HO
[high Intensity] Fluorescent indirect light fixtures is the same or less
than metal halide, but the maintenance and energy costs will be lower. One
court may require 18 ten-lamp T5 fixtures.
(ix)
Ceiling
A suspended ceiling is
not contemplated.
(x) Heating and
Cooling (Terminal Energy)
Two Modine MT 120 high
intensity infrared heating units -
one at each end of the building - might be sufficient to heat the said
structure at a total cost for the two heaters of c. $1,200.00 USA.
(xi)
Plumbing
An Envirolet electric
waterless toilet by Sancor might cost $1,400 USA. No cost for
chemicals, incinerating, or septic. To bring water into the building and
associated plumbing and sewer line costs could easily exceed this amount.
(xii)
Wiring Installation
Electrical wiring costs
will be at the standard rate for the recommended lighting system.
(xiii) Automatic
Active Fire Suppression System
The cost is unknown until
the type of system is determined.
(xiv) Court (contractor)
Novacrylic Ultracushion being an acrylic surface
applied to new asphalt or new
concrete built upon on a base costs approximately $11,000 USA per
court (i.e. over and above the cost of the asphalt or
concrete base).
Generally, many cushion
coatings will add approximately 0.95 cents USA per square foot to the
overall cost of a court, is a one time investment, and if amortized over 20-25
years, the extra cost if increased user participation is the goal may be worth it.
In comparison:
- Hard courts,
such as the Cromarty Tennis Club's four existing outdoor "fast game" courts, covered
with a simple acrylic surface - adjusted for speed by the amount,
type and sand - are less expensive, costing circa $18,000 USA including
the asphalt base.
- Har-Tru which is a clay/fast-dry surface constructed
over a rock base might cost $15,000-$20,000 USA for an indoor installation.
- Natural
clay and fast-dry courts with above ground irrigation systems typically
cost between $18,000 USA and $24,000
USA per court.
- Fast-dry
courts with subsurface irrigation systems are usually more expensive
(more involved construction),
and range between
$25,000 USA and $30,000 USA
per court.
- Synthetic
granular courts (an experienced contractor
and available materials is critical), usually cost between
$25,000 USA and $30,000 USA
per court for outdoor installations, and $15,000
USA to $18,000 USA
for indoor installations.
All
soft courts require some sort of regular maintenance and
how much to spend initially versus how to spend on annual up-keep,
might be the determining factor.
A court with above-ground irrigation might
be less expensive to construct than a subsurface irrigated court, but more
expensive to maintain over the life of the court because of its greater need
for water and daily maintenance.
Synthetic clay courts, meanwhile, require no
watering at all and significantly less maintenance.
(xv)
Interior Amenities
The added cost for
padding the columns will be minimal.
(xvi) Landscaping
(a) Cromarty Tennis
Club Area
The
additional security
fencing price will
be relatively minor compared to other input cost. However, total cost here
is impossible to determine until the building is actually sited.
(b) Sydney Area
Unknown
(c) CBU
Unknown.
(B) Operational Costs
Because operational costs will contribute to
2/3rds of the total cost of the public facility over 20-25 years, great savings are
possible here if the initial design addressed annual energy consumption and
maintenance issues in the most efficient manner possible.
(i) Annual Energy consumption
(a) Lighting
In 2005, the total
electricity charge for the Cromarty Tennis Club's 4 outside courts that included 24
court light fixtures (Metal Helix - 1500-Watts each) was just $867.00 CND
with Kwh used being only 6180. Clearly, the lighting requirements of a
public
indoor facility would exceed that dollar amount, but fixture type and
number can dramatically reduce cost. For example, whereas a single
indoor Tennis Court using 14 indirect 1,000-Watt Metal Halide Lamps,
operating 17 hours per day, at $0.10 USA per KWH, would cost $771 USA
per month [510 or 527 hours], that same court using the Courtlite Direct
Recreational energy efficient lighting system, will deliver better
lighting quality, and only cost $286 USA per month [
http://www.courtlite.com/main.htm ].
In other words: Approximately $1.51 USA versus $0.56 USA
[$0.70 CND] maximum per hour.
(b) Heating
Because energy costs
will no doubt continue to rise, a high insulation value for
the building envelope and a high efficiency heating
system is critical to minimize their cost effects.
An infrared gas heater
is at least 50% more fuel efficient than a hot-air system.
http://store.h-mac.com/heloca.html has an
interesting free downloadable heat load calculator in excel format where
approximate calculations can be easily made. For example, for a building
that measured 60'x120' and say averaged 30' high overall, with the walls
R20, the ceiling R32, total exterior insulated door openings of 96
square feet, no concrete slab insulation other than an insulation skirt,
and 55 F degrees
[12.7 degrees C]
inside when the outside temperature is 0 F, the
calculated loss can be measured as 240,834 BTUHS (or 70,564 watts)
(where BTUHS or BTUH Sensible = Pounds of air per hour x change in air
temperature x 0.24). The British Thermal Unit per Hour content of
propane is normally about 91K or .29307107 watts.
The consumption of
propane is measured in litres with propane having an energy content of
about 25.3 MJ/L [megajoules per litre] or, more precisely 24,500 BTU of energy per litre.
Superior Propane's
locked-in 2006 commercial unit price for propane is presently
$0.49 CND per litre. Given the estimated heat loss for the proposed
minimal sized building, it would cost approximately $4.82 CND per hour
to heat this structure to 55 degrees F [12.7 degrees C].
(ii) Maintenance Expenses
(a) Building
(1) A steel building is
virtually maintenance free.
(2) For a bubble,
spots can be removed with warm, clear water. Special cleaning liquids
are required once a year. In case of damage,
the bubble must be taken down. Smaller injuries can repaired with a
repair set (glue and patch material); more severe damage may have to be
repaired by the manufacturer.
A bubble can be
folded and stored only when it is dry and placed in a rodent free
environment.
Air structure fabric membranes typically
have a life expectancy of 10 to 12 years.
(b) Court
Washed occasionally
to get maximum life.
The wearing
surface of a Ultrcushion court is
non-fading, high performance 100% acrylic, and is
environmentally friendly. The top surface, the Novacoat in the
Novacrylic combination surface, will look attractive for 5-8 years -
depending on the quality of housekeeping - between recoating, with a
minimum amount of maintenance. It is coloured all the way through from
the top to the substratum. In the event of damage, such as gouges from
racquets, vandalism, court equipment, etc., the damaged area will be the
same colour as the rest of the court.
Average life of 12-15
years outdoors before requiring major work. Much longer lifespan
indoors.
From time to time a
net will need be purchased.
- Typical Tennis Court
Maintenance Considerations:
(c) Heating
System Maintenance
Utilization of a
propane heating system requires a maintenance contract to ensure routine
checks and safe operation.
(d) Automatic
Active Fire Suppression System Inspection, Testing and Maintenance
An active fire suppression
system (if installed) will need to be inspected monthly and annually.
Consequently a maintenance contract
will be required to meet insurance requirements.
(e)
Security and Fire Monitoring; Lock and Key System
An annual fee will be
required for the security and fire monitoring system.
(iii)
Insurance (Property and
Third-Party)
Insurance costs for a
pre-engineered steel structure such as the proposed public facility - with few
combustibles, low occupancy fire-risk, and fully sprinklered - should draw Sydney's lowest possible rate. For example, for a steel structure
(concrete slab and footings not included), with a materials and assembly
construction cost of $200,000 CND and insured for 80% of value at an annual
rate of $0.08 CND per $100.00 CND of coverage, the annual insurance premium
ought to be circa $128.00 CND
The existing outdoor
third-party insurance should be extended to functions within the public facility
since the tennis function is the same here. Further consideration should be
given to obtaining insurance to cover other events such as extra-ordinary
fund-raising and specified alternate than tennis use (like yoga
lessons).
As a matter of
comparison, the existing insurance cost for the outdoor summer programme
[both property and third party liability] is $935.00 CND.
(iv)
Insurance (Directors
and Officers Liability)
This insurance would
protect the board from wrongful act
suits. For a non-profit existing society like the Cromarty Tennis Club for
example, without employees, etc., such
a policy would be relatively straightforward. A $2,000,000.00
coverage is the minimum which ought to be purchased. Present costs vary from
c. $750.00 ($1,000,000.00
coverage) to c. $1250.00 ($2,000,000.00
coverage).
(C)
Revenue Projections, Source of Funding, and Profitability
Analysis
The goal of this public
facility is to generate
sufficient revenue to cover off a 12-month operating expense of lights, heat,
security, maintenance, as well as a yearly amortized
capital cost. Naturally, a business plan that was able to access any initial
non-repayable matching or lesser grant from a federal or provincial capital programme
would go far to ensure profitability.
(i) Ideals
Maximum revenue
projections could be based on a 360 year 17-hour day player operation, or
6120 operational hours per year, with the user fee rooted in singles and
doubles play. For example:
(1) 17 hours per day
x 360 days x 4 players would generate 24,480 summer-winter player hours
(2)
17 hours
per day x 360 days x 2 players would generate
12,240
summer-winter player hours (3) 17 hours per day x 208 days x 4
players would generate 14,144 winter player hours (4) 17 hours per
day x 208 days x 2 players would generate 7,072 winter player hours
(5) Any combination based on the above
In this scenario, a
profitability analysis would need to consider that all of these hours would
incur an hourly player-required lighting cost. Furthermore, the 208 17-hour
winter playing days (November 1-May 31) would attract 3536 of player-required heating costs, with another
1456 hours of building-required heating costs when the public facility was not
operational late at night and early in the morning (i.e. 7 additional hours
per day).
(ii)
Reality
Then there
is reality in that these ideal targets may never be met, but as a tool, they
are suggestive.
In the
everyday world, one would combine the yearly operational costs and the
firmed up yearly amortized capital cost, and then calculate what it would take to generate the required revenue to produce no less than a
financially break-even operation.
In the
executive summary, the following capital scenario was provided:
"The
capital funding of such a public facility will be more difficult. For example,
at a 6% mortgage rate amortized over 20 years, the payment for a
$200,000.00 obligation would be approximately $1,425.00 per month or
$17,100 per year. However, if it were only $100,000.00, then it would be
$712.00 per month or $8,550 per year; and etc."
Furthermore,
if, the rate were 8% amortized over 20 years, the payment for a $200,000.00
obligation would be approximately $1,675.00 per month or $20,100 per year.
And so on.
According to
a previous discussion [lighting, heating, maintenance expenses, insurance],
year to year operational costs are much less when compared to the yearly
capital load.
Reality
suggests strongly that a reasonably priced November 1-May 31 winter
programme just by itself would fund the total yearly operational and capital
costs, and that any funds generated by a summer indoor programme (June 1 -
October 31) would be gravy. For example, during the winter session, the
number of available hours (less 4 storm days) would be as follows:
PRIME
TIME (1571 hours or 53 hours per week) - Non-Retired Players Have
Priority
(1)
Every night: 6 pm-11 pm - 5 hours x 208 days or 1040 hours
(2)
Weekend days: 9 am-6 pm - 9 hours x 59 days or 531 hours
OFF-HOURS (1341 hours or 45 hours per week) - Retired and Non-Retired
Players have Equal Priority
(1)
Week Days: 9 am-6 pm - 9 hours x 149 days or 1341 hours
Clearly,
given a reasonable per hour charge, one would expect prime hours to be fully
booked and off-hours booked to a lesser degree. Adding the actual results of
the two bookings together, a winter court fee as low as $10.00 per hour (and
certainly $20.00) could conceivably meet all capital and operational
obligations for the entire year!
From a
player's perspective, a low winter hourly charge would encourage multiple
sessions per week (whether singles or doubles), whereas a higher charge
would obviously discourage both multiple per-week and singles play.
(iii) Fees
The Centre will charge an hourly,
tennis booking fee, first come, first serve, with one exception, when the
Centre is running a group community tennis programme as pre-scheduled on its
website.
The summer outdoor operation at the Cromarty Tennis Club
has successfully sustained itself now for many years
with a relatively low membership
fee, with an active volunteer participation, and
with some key grants. The
summer indoor public facility (which will utilize hourly rather than yearly
membership fees) should have a similar goal in mind - i.e. low hourly rates,
active volunteers.
In the winter, highly
motivated recreational and competitive players, as well as large playing
families - competing over one court - will want two to three sessions per
week. In essence, this is a multiple participation use that must be
encouraged through
an affordable hourly rate.
An
economically-sound indoor user regime
might
want to take the following format:
(a)
Public Indoor Winter Programme
(November 1 –
May 31)
Clearly, operational
charges will be higher during the winter months and the fee will need to reflect how best to
recoup costs. A realistic per-hour user charge (i.e. based on 60 minutes, not 40
minutes, not 90 minutes, etc.) would probably
best meet this requirement.
Player fairness would
be ensured through an on-line
internet booking system similar to the one previously used by the
Cromarty Tennis Club
As already noted
above, the number of available prime time hours per week would be 53
with non-retired players having a priority. Another 45 hours per week
would be available to retired and non-retired players during the
off-times.
(b)
Public Indoor Summer Programme (June 1-October 31)
During the summer
months public participation would no doubt fall off due to the wide
variety of competing recreational activities including outdoor tennis.
To encourage the participation of outdoor tennis clubs in the area, as
well as the public in general (including the travelling visitor), a
lower fee (i.e. based on 60 minutes, not 40 minutes, not 90 minutes, etc.)
would be charged for those wishing to use the public facility.
A
paper booking system
like that used for the Cromarty Tennis Club's outside courts would be
best as this would assure both planned as well as spontaneous play (e.g.
when the outdoor courts were fully occupied, or when visitors arrived).
(iv) Cost-Recovery
Winter School, After-School, and Junior Development Tennis Programmes
A winter school
tennis programme should be designed as an
option for those now using the existing Ski Ben Eoin
programme. For example, youth/school ski program rates
there range from a weekend charge of $27.00 for a lift pass, lesson and
rental to a $3.00 charge for a midweek lesson only. In particular, the
tennis programme should concentrate on midweek bookings so as not to intrude
upon the more popular tennis weekends. During this midweek period, the ski
program charges $20.00 for a lift pass, lesson and rental and $3.00 for a
lesson only, fees with which a public indoor facility could easily compete.
A separate winter
"after-school" tennis programme modeled upon the Cromarty Tennis
Club's summer one might be
quite popular as well.
A winter junior
development programme, separate from the above school programmes, designed
to fast-track the CBRM's best players to national prominence is a must.
Presently these players are at a national disadvantage during winter months
as they have no place to maintain and increase their skills.
Within the cost-recovery
aspect of the winter school programme, there would certainly be sufficient
funds to entice a retired player(s) to provide the required lesson and
supervisory component; Similarly there would be enough for a stipend to
entice a player of, say Bill Buckland's national calibre (5th in his
category), to provide the required lesson and mentor component for a junior
programme.
(v) Extraordinary
Club Closed Programmes
Specialized programmes
designed to raise
Cromarty Community Indoor Tennis Centre money (e.g. private lessons, exhibition tournaments,
etc.) would not be deterred by the whims of weather and could thus be quite
appealing because of the certainty of an event being held.
(vi) Alternate Uses
Other groups, such as yoga, are known to be looking
for an inexpensive, reliable public facility where to hold their programmes.
(vii) Yearly Operating Grants
CBRM might be
willing to match the summer grant amount for a winter programme if it
included a junior and school programme.
Frank Bruleigh, CBRM
Recreation Department, 320 Esplanade,
Sydney, Nova Scotia, B1P 7B9,
wfbruleigh@cbrm.ns.ca
, should be consulted on this.
Any winter fitness
programme that the Cromarty Community Indoor Tennis Centre might run during the winter in association with
schools might be eligible for a provincial or federal grant, now or in the
future:
(viii) Donations and
Bequests
Tax deductible donations
and bequests would be possible if the public indoor facility were operated as a
registered non-profit charitable trust.
(vix) Corporate Sponsorships
Sponsorships are an integral part of the
marketing and promotional activities of many companies, including RBC which
promotes amateur sports -
http://www.rbc.com/sponsorship/guidelines/prog_02.html

|